Design and Specifications Development Phase (Pre-Bid Award):

  • Assist Owner with selection of systems appropriate for commissioning.
  • Assist Owner and Design Team in developing desired system maintenance and performance criteria for selected systems.
  • Develop appropriate commissioning plan/specification documents for selected systems.
  • Review proposed design documents for constructability and maintainability issues on selected systems.
  • Attend pre-bid meetings to answer commissioning related questions.

Construction Phase (Post Bid Award):

  • Meet with selected contractors to review commissioning requirements and establish a tentative commissioning schedule.
  • Review submittals for selected systems.
  • Attend job site meetings to monitor progress and communicate issues.
  • Develop specific installation verification checklists for selected systems.
  • Perform installation verification and note all deficiencies
  • Verify systems completion and readiness for functional testing.
  • Witness contractor's initial equipment/systems start-up procedures.
  • Develop specific performance testing procedures for selected systems.
  • Perform functional tests on selected systems and record results.
  • Document all noted functional deficiencies.
  • Perform re-testing of systems that fail to meet test criteria.

Project Close-out and Post Construction Phase:

  • Assist in the appropriate resolution of all outstanding issues.
  • Verify completion and/or scheduling of specified systems training.
  • Review provided O&M manuals.
  • Review provided as-built drawings.
  • Verify all commissioned systems are complete and recommend acceptance to the owner.
  • Prepare and submit final commissioning report.
  • Perform any necessary seasonal testing and attach addendum to final report.
  • Monitor post occupancy and warranty period performance. Assist Owner with warranty issues as requested.